Start of the drain
Both are optional. Fill in either to get levels or laser readings at every peg.
Levels and readings are to the invert (inside bottom) of the pipe. Laser readings get bigger as the drain goes down.
Drain legs
One row for each straight length between bends, junctions or pits, in order from the top end.
Usual minimum grades
| Pipe | Minimum grade | Fall per 10 m |
|---|
Sanitary drains, from AS/NZS 3500.2. Some fixtures, authorities and site conditions need more. Stormwater grades are set by AS/NZS 3500.3, the plans and the local council.
Quoting the drainage?Price the pipe, fittings and labour from your supplier’s list, get the quote signed on site and invoice in one tap.
Try Wattlebase free for 30 daysLong section
Peg levels
A guide only. Check levels on site, the approved plans, the sewer connection depth and AS/NZS 3500. Grades are kept to the nearest millimetre, so measure from the start each time rather than adding up small steps.